A PP sheet FAT checklist should verify that the fabricated chemical equipment matches the approved drawing, material schedule, weld and leak-test records, functional interfaces, and shipment configuration before it leaves the factory. FAT is not a replacement for design approval or a single pressure test. It is a controlled witness point where the buyer and fabricator confirm what was built, what was tested, what remains open, and what evidence will travel with the equipment.
PP sheet FAT checklist: define the boundary before fabrication is complete
Factory acceptance testing becomes inefficient when the buyer and fabricator discover the scope at the inspection table. The FAT notice, inspection and test plan, or purchase specification should define the equipment tag, approved drawing revision, witness or hold points, attendees, test instruments, required records, acceptance criteria, and the decision authority for deviations.
IEC 62381:2024 describes FAT, FIT, SAT, and SIT as project-specific activities with checklists adapted to the process or plant equipment. It is written for automation systems, not PP sheet fabrication, but its useful principle is transferable: agree the test scope, responsibilities, evidence, and release decision before the test starts. A PP equipment FAT should therefore be tailored to the actual tank, duct, scrubber, enclosure, or cabinet rather than copied from a generic form.
Keep the boundary clear. FAT can confirm fabrication quality, interfaces, documentation, and agreed functional checks at the factory. It does not automatically prove site installation, final chemical compatibility, building-code compliance, field support loads, or the performance of connected equipment that was not present for the test.

Verify identity, configuration, and material traceability first
Start the PP sheet FAT checklist with items that cannot be corrected by a late cosmetic repair. Confirm the equipment tag, serial or project number, approved drawing and revision, bill of materials, nozzle schedule, orientation marks, and the intended shipping split. Then match the material records to the fabricated parts:
- PP grade, color, nominal thickness and applicable tolerance.
- Sheet or welding-rod lot identification and receiving inspection record.
- Backing, inserts, gaskets, fasteners, frames, valves, instruments, or other non-PP components.
- Approved substitutions, repair records, nonconformance dispositions, and as-built changes.
- Surface condition, protective film, edge integrity, and cleanliness before packing.
QEEHUA’s internal working rule is inspect first, process second. At FAT, that means the inspector should be able to trace a visible panel or weld to the material and fabrication record instead of accepting a general statement that “PP was used.” The PP sheet material traceability guide provides a companion record structure for receipt through fabrication handover.
Check dimensions, geometry, and interfaces against the approved drawing
A FAT checklist should turn the approved drawing into measurable inspection points. Check overall length, width, height, wall or panel thickness where specified, nozzle centerlines, flange faces, access openings, drain locations, support contact points, lifting points, and the orientation of labels and flow arrows. Use calibrated tools appropriate to the tolerance; record the actual value rather than writing only “OK.”
For a large PP tank, duct, scrubber, or enclosure, inspect the interfaces that are most likely to create site rework: mating flanges, flexible connections, fan or damper transitions, pump penetrations, cover clearances, removable panels, and the split lines used for transport. Confirm that the equipment can be lifted, moved, installed, and serviced without removing a component that the owner expected to remain in place.
Do not convert a FAT dimensional check into a universal PP design guarantee. The project drawing, support calculation, installation tolerances, and site survey define the acceptance values. Record any field dimension that cannot be verified at the factory as an open site item instead of silently closing it.
Review welds and containment evidence without duplicating the test plan
The FAT checklist should confirm that weld inspection and containment tests were completed to the approved procedure, while the detailed method and acceptance limits remain in the project inspection and test plan. Review weld IDs, visual inspection, repair history, test coupons or procedure qualifications where required, and the leak, hydrostatic, vacuum, or functional test record applicable to the equipment.
For tanks and liquid-retaining equipment, verify test medium, test duration, instrument identification, temperature or environmental conditions, observed leakage, and disposition of any repair. For exhaust ducts or scrubbers, confirm the defined leak or airflow check and the status of access doors, drains, spray headers, mist eliminators, and flexible interfaces. The PP chemical-tank leak-test record guide و PP tank weld inspection checklist cover those narrower evidence packages.
Check that welds are clean, dry, and free from visible holes, cracks, lack of fusion, or unapproved grinding damage. Do not force a panel into alignment during FAT or use a cosmetic touch-up to hide a structural or containment issue. Any repair should have a clear location, cause, method, reinspection, and approving signature.

Test functional items that affect site installation
Not every PP fabrication needs an energized performance test, but every FAT should confirm the functions that the factory can realistically demonstrate. Agree the list before the witness date:
- Valves, dampers, drain points, sampling points, removable panels, covers, and access doors operate through their intended range.
- Gaskets seat correctly and fasteners, clamps, hinges, latches, and supports are installed in the specified materials and positions.
- Spray headers, demister retainers, baffles, trays, or internal components are installed, removable, and correctly oriented.
- Labels, flow arrows, equipment tags, lifting marks, connection points, and shipping split marks are legible and match the drawing.
- Drain paths, cleanout access, and low points are visible and can be reached for the planned maintenance task.
When connected pumps, fans, controls, or instruments are not included in the factory test, write “interface verification only” and identify the later SAT or commissioning check. This avoids claiming that a PP vessel or duct assembly has demonstrated a complete process result when only its fabricated interfaces were reviewed.
Control punch-list items before approving release
A FAT is not complete because the inspection meeting ended. Each observation should be classified as accepted, corrected and rechecked, accepted with a named concession, or open for site action. The release page should identify the responsible person, due date, evidence required, and whether the item blocks shipment.
| FAT area | Verify before shipment | أدلة الإفراج |
|---|---|---|
| Identity and drawing | Tag, serial/project number, approved revision, equipment split, orientation and connection schedule | Signed drawing mark-up and equipment identification record |
| Material and welds | PP grade/thickness, lot records, rod match, weld IDs, visual inspection and repair disposition | Material traceability pack, weld log and inspection record |
| Dimensions and interfaces | Overall dimensions, nozzles, flanges, access, supports, drains, lifting points and mating components | Measured FAT sheet and approved deviation list |
| Containment and function | Applicable leak, hydro, vacuum, airflow, valve, drain, access and component checks | Test record with calibrated instrument IDs and results |
| Surface and preservation | Cleanliness, protective film, edge protection, capped openings, dry storage and corrosion/impact protection for non-PP parts | Pre-packaging photographs and preservation checklist |
| Documents and punch list | Manuals, SDS or data sheets, drawings, certificates, spares, open items, concessions and sign-off responsibilities | Indexed handover package and release authorization |
OSHA process-safety guidance emphasizes that inspection and test records should identify the equipment, date, person performing the work, description of the test, and results. That is a useful minimum for a PP sheet FAT checklist even when the project is not governed by OSHA PSM. Keep the file retrievable and linked to the equipment identifier.
Prepare the equipment for transport without losing the evidence
Shipment preparation is part of FAT release because handling can undo a passing inspection. Confirm that the packaging plan protects welds, gasket faces, machined edges, nozzles, access panels, and clean internal surfaces. Cap or cover openings, use supports that do not point-load a PP panel, keep the equipment flat or in the approved orientation, and mark lifting points and center of gravity where required by the project.
QEEHUA’s PP-use guidance calls for protective film when surface requirements are high, separation from metal edges and hard debris, and suitable packaging for semi-finished or finished parts. Record photographs before closing the crate or wrapping the equipment. If the shipment is split into modules, match each package to the drawing, packing list, connection marks, and reassembly instructions.
استخدم PP exhaust-duct handover document guide for a related document structure, then add the project’s FAT certificate, punch-list closure, packing photos, lifting notes, and site reassembly requirements. The goal is that the receiving team can identify what passed at the factory and what still must be checked after installation.

Related QEEHUA process video: this precision-cutting reference shows why the released drawing and panel identity should be controlled before fabrication and packing. It is not a FAT certificate, leak test, or shipment acceptance record.
Video reference: PP Sheet Cutting Process: Precision Cutting | QEEHUA, from the approved QEEHUA playlist. Manufacturing context only.
الأسئلة الشائعة
What is the difference between a PP sheet FAT and a leak test?
A leak test evaluates a defined containment condition. A PP sheet FAT is the wider factory acceptance review that can include identity, dimensions, weld records, leak or functional tests, interfaces, documents, punch-list status, and shipment readiness.
Can FAT be completed remotely for fabricated PP equipment?
It can when the inspection and test plan defines the remote witness method, camera views, measurement records, instrument evidence, document access, and authority to accept deviations. Critical tests or concealed details may still require an agreed physical inspection.
What should block shipment after a PP equipment FAT?
Open containment failures, unidentified material, unapproved weld repairs, incorrect nozzles or supports, unsafe lifting or packaging, missing required test evidence, and unresolved deviations that affect installation or operation should block release until formally accepted or closed.
Which documents should accompany a PP chemical-equipment FAT?
Typically include the signed FAT checklist, approved and as-built drawings, material and welding records, applicable leak or functional tests, calibration evidence, inspection photographs, manuals or data sheets, packing list, lifting and reassembly instructions, punch-list closure, and release authorization.
Send the approved drawing, equipment tag, inspection and test plan, material and weld records, test requirements, packing method, and owner handover list. Contact QEEHUA for a project-specific factory acceptance review.